05 signal flow during plasma cutting, 06 sc 3000 operation sequence, Signal flow during plasma cutting -9 – Tweco SC-3000 User Manual

Page 49: Sc 3000 operation sequence -9, Sc-3000

Advertising
background image

SC-3000

Manual 0-5100

4-9

OPERATION

4.05 SIGNAL FLOW DURING PLASMA CUTTING
















From To

Signal

CNC

Initial Pos. Start

Plasma

Separate Ignition

Plasma

CNC

Ok To Move

Delay Time

Control Active

Surface of work piece

Reference Position

Cutting Height

Plasma

Time / Track

Cutting On

Cutting Off

Pierce Height

Elevation Height

Start XY

Retract Position

Corner

1

2

3

4

5

6

State

Clearance

Art # A-08934_AB

SC-3000

SC-3000

SC-3000

SC-3000

SC-3000

SC-3000

SC-3000

SC-3000

OK PS

Plasma

CNC

4.06 SC 3000 Operation Sequence

Definitions:

THC

• Torch Height Control, in this case refers to the SC3000.

Initial Position Start

• Input where Start from CNC is applied to start THC’s height finding sequence.

Ready (Start XY)

• Input to THC for arc transferred signal from plasma (OK to Move).

Advertising