Enclosure Installation

10. Installation: Lift up the contactor and place the bottom enclosure underneath. The end with the Oblong slot in

the bottom and the four detents goes toward the front of the Cutmaster. Slide the Contactor completely forward

and attach the parts to the original contactor mounting points. Tighten all electrical connections to 17 +/-1 In/

lbs. Lifting the Cutmaster and shining a light below the base panel will illuminate the mounting holes to assist

with alignment. Orient contactor wires so that they are above the detents in the bottom enclosure LOAD (T1-4)

side, as shown. The wire #7 detent will also have contactor control wires #1, #2, #5 and #6 laid underneath, as

shown. Push wires #1, #2, #5 and #6 between contactor and the box wall. Input AC power cord wires will separate

between the two detents on the LINE (L1-4) side of the box bottom. If a 3 phase AC power cord is used, populate

L1 and L2 into the furthest back (inner)detent and L3 to the front (outer) detent.

Figure 18: Contactor Bottom Figure 19: Contactor Wire Routing Load Side

Figure 20: Contactor Wire Routing Line Side