CHAPTER 2: INSTALLATION

Page

18 of 162 PR2: 05/09/12

Benchmark 1.5LN Dual-Fuel Low NOx Boiler

Operation and Maintenance Manual

OMM-0041_0C

GF-121

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913 • Ph: 800-526-0288

IRI Gas Train Kit

2.7.3

The IRI gas train is an optional gas train configuration which is required in some areas for code

compliance or for insurance purposes. The IRI gas train is factory pre-piped and wired. See

Appendix F, Drawing AP-A-830 for details.

2.8 AC ELECTRICAL POWER WIRING

The AERCO Benchmark 1.5 Electrical Power Wiring Guide, GF-4060, must be consulted prior

to connecting any AC power wiring to the unit. External AC power connections are made to the

unit inside the Power Box on the front panel of the unit. Remove the front door of the unit to

access the Power Box mounted directly above the Control Box. Loosen the four Power Box

cover screws and remove cover to access the AC terminal connections inside the Power Box

(Figure 2-7).

NOTE

All electrical conduit and hardware must be installed so

that it does not interfere with the removal of any unit

covers, inhibit service/maintenance, or prevent access

between the unit and walls or another unit.

UPPER RIGHT CORNER OF FRONT PANEL

TERMINAL BLOCK

Figure 2-7: AC Input Terminal Block Location

Electrical Power Requirements

2.8.1

The AERCO Benchmark 1.5 Boiler accepts 120 VAC, single-phase, 60 Hz @ 20 A. The Power

Box contains a terminal block as shown in Figure 2-8. In addition, a wiring diagram showing the

required AC power connections is provided on the front cover of the Power Box.
Each Benchmark 1.5 Boiler must be connected to a dedicated electrical circuit. NO OTHER

DEVICES SHOULD BE ON THE SAME ELECTRICAL CIRCUIT AS THE BENCHMARK

BOILER.
A double-pole switch must be installed on the electrical supply line in an easily accessible

location to quickly and safely disconnect electrical service. DO NOT attach the switch to sheet

metal enclosures of the unit.
After placing the boiler in service, the ignition safety shutoff device must be tested. If an external

electrical power source is used, the installed boiler must be electrically bonded to ground in

accordance with the requirements of the authority having jurisdiction. In the absence of such

requirements, the installation shall conform to National Electrical Code (NEC), ANSI/NFPA 70