4.2.1

Required Tools & Instrumentation

The following tools and instrumentation are necessary to perform combustion calibration of

the unit:

Digital Combustion Analyzer: Oxygen accuracy to ± 0.4%; Carbon Monoxide (CO)

and Nitrogen Oxide (NOx) resolution to 1PPM.

16 inch W.C. manometer or equivalent gauge and plastic tubing.

1/4" NPT-to-barbed fittings for use with gas supply manometer or gauge.

Small and large flat blade screwdrivers.

Tube of silicone adhesive

4.2.2

Installing Gas Supply Manometer

The gas supply manometer (or gauge) is used to calibrate the gas pressure to be monitored

on the downstream side of the SSOV during the Combustion Calibration procedures

described in paragraph 4.4.
The gas supply manometer is installed at the downstream location on the 1/4” NPT port

shown in Figure 4-1. Note that a 1/4” plug must be removed from the port in order to install

the manometer.

Figure 4-1: Manometer Installation Location for Combustion Calibration

MANUAL SHUTOFF

VALVE

NATURAL

GAS SSOV

PROPANE

GAS SSOV

NATURAL

GAS INLET

PROPANE

GAS INLET

TO AIR/FUEL

VALVE

NATURAL GAS HIGH

GAS PRESSURE

SWITCH

PROPANE HIGH GAS

PRESSURE SWITCH

1/4” NPT PLUG (Install

Combustion Calibration

manometer here)

PROPANE

PRESSURE

REGULATOR

FEEDBACK LINE

NATURAL GAS

PRESSURE

REGULATOR

FEEDBACK LINE

LEAK DETECTION

BALL VALVE