TOP LOAD BAG AND CAGE INSTALLATION

1. Inspect the cage for any signs of damage, warping, bent wires, or missing

welds.

2. Inspect the filter bag for any signs of mold, mildew, ripped seams, or holes.

3. Lower the closed end of the bag through the hole in the tube sheet.

4. With your hands, “kidney shape” the snap band bag top in order to fit and

align it within the tube sheet hole.

5. Fit the groove of the snap band to the I.D. of the tube sheet hole and allow it

to expand and audibly snap into place. If the band will not snap into place
initially, do not push on the “dimple” as doing this will permanently damage
the snap band. Instead, kidney shape the snap band from the opposite side of
the band. Then you can allow the band to expand and audibly snap into
place.

6. Check the fit of the snap band to the tube sheet. It should be even in height

above the tube sheet around the entire circumference, which will confirm to
the installer that the tube sheet is centered and well secured into the middle
groove of the snap band.

7. Lower the cage into the bag and press that cage top down into the bag’s snap

band I.D. When in position, the rolled flange of the cage top will rest on the
tube sheet and the bag and cage assembly will be rigidly mated. The O.D. of
the cage top provides a compression fit to the I.D. of the snap band.

8. Disconnect the drive chain to allow the pulse arm to rotate freely to access

the holes under the arm if necessary.

9. Replace access doors and tighten accordingly. You are ready to begin start-

up procedures if all other preceding tasks and hook-ups are completed.