Configurations, dimensions, and, Clearances -8, 1 configuration requirements – Reznor VR Unit Installation Manual User Manual

Page 7: Configurations, dimensions, and clearances, Uncrating/ packaging (cont’d)

Advertising
background image

Form I-VR, P/N 205202 R13, Page 6

4.1 Configuration

Requirements

Depending on the length and size of the heater, the heat exchanger sections

may be installed in various configurations. Optional “L”-shaped, 5-foot, and

“U”-shaped heat exchanger tubes are available to adapt the heaters to these

configurations (Option UC2 for “L”; Option UB3 for “U”; Option UA1 for 5-foot

heat exchanger tube).
Model VR/GVR heaters may be installed in the configuration lengths shown

in the table on page 7. Only straight tubes are used to identify length. The

combustion chamber is always the first 10 ft (3.1M) length. The straight heat

exchanger tubes represent each additional 10-ft (3.1M) or 5-ft (1.5M)
Comply with the requirements listed below and the lengths in the table.

• Sizes 100 and 125 require 15 ft (4.6M) of straight tube length before installing an

optional “U” or an “L” tube.

• Size 150 requires 20 ft (6.1M) of straight tube length before installing an optional

“U”, “L”, or 5-ft (1.5M) tube.

• Sizes 175 and 200 require 30 ft (9.1M) of straight tube length before installing an

optional “U”, “L”, or 5-ft (1.5M) tube.

• Maximum of one “U” tube per system (do not use with “L” tubes).

• Maximum of two “L” tubes per system (do not use with “U” tube)

• Maximum of two 5-ft (1.5M) tubes; 5-ft tubes may be used in a layout with a “U” or

“L” tube

• On a “U” configuration, the straight tube length on the burner side of the “U” must

be equal to or longer than the tube length on the exhaust side.

• Exhaust tube must always be a 10-ft (3M) tube.

4. Configurations, Dimensions, and Clearances

FIGURE 1 - Tube

Cartons include

Tubes, Reflectors,

Hangers, Brackets,

Couplings, and

Hardware

Important NOTE: Before

installation, wipe any

excess corrosion inhibitor

from the heat exchanger

tubes. Failure to do so

could result in excessive

smoke from the surface

of the tubes on first

startup.

3. Uncrating/

Packaging

(cont’d)

(NOTE: Chain for hanging is not included. Use either an optional hanger kit (Option

CK11) and/or a turnbuckle kit (Option CK12-18) or field-supplied hardware. See sus-

pension requirements in Paragraph 5.)

Packaging Scheme for 10’ Straight Tubes

Pkg ID* Pkg P/N Contents

VRE

205204 (1) Combustion Chamber Tube; (1) Heat Exchanger Tube

VRF

205205 (1) Combustion Chamber Tube; (2) Heat Exchanger Tubes

VRG

205206 (2) Heat Exchanger Tubes

VRH

205151 (3) Heat Exchanger Tubes

Tube Packages Required by Length of System Each tube package includes

required hardware for tubes and

reflectors. Extra hardware packages

are available as parts.

Length

Qty Pkg P/N Qty Pkg P/N

20 ft system requires 1 205204 --

--

30 ft system requires 1 205205 --

--

Pkg ID Pkg P/N

Hardware Pkg

40 ft system requires 1 205204 1

205206

VRE

205204

P/N 209401

50 ft system requires 1 205204 1 205151

VRF

205205

P/N 209402

60 ft system requires 1 205205 1

205151

VRG

205206

P/N 209403

70 ft system requires 1 205205 2

205206

VRH

205151

P/N 209404

Accessory Cartons - All field-installed options are shipped in separate car-

tons. Be sure all parts are at the installation site.

WARNING: Do not

install a heater in a

length or configu-

ration that is not

permissible for the

Size. See Hazard

Levels, page 2.

Refer to Form T-VR-

CNFG (available from

your distributor), for a lay-

out view of all allowable

configurations.

*Tube Package ID is the

same for Model VR and

Model GVR heaters.