14

VENTING INSTALLATION

INSTRUCTIONS

Continued

INSTALLATION FOR VERTICAL
TERMINATION

NOTICE: Use rigid pipe only. Flex

venting is not to be used with a

vertical termination.

1. Determine the route your vertical venting will

take. If ceiling joists, roof rafters, or other

framing will obstruct the venting system,

consider an offset (see Figure 21) to avoid

cutting load bearing members.

Note: Pay special attention to these installa-

tion instructions for required clearances (air

space) to combustibles when passing through

ceilings, walls, roofs, enclosures, attic rafters,

etc. Do not pack air spaces with insulation.

Also note maximum vertical rise of the vent-

ing system and any maximum horizontal

offset limitations. Offsets must fall within the

parameters shown in Figure 22.

2. Set the fireplace in desired location. Drop a

plumb line down from the ceiling to the posi-

tion of the fireplace exit flue. Mark the center

point where the vent will penetrate the ceiling.

Drill a small locating hole at this point.

Drop a plumb line from the inside of the roof

to the locating hole in the ceiling. Mark the

center point where the vent will penetrate the

roof. Drill a small locating hole at this point.

X

12

Roof Pitch is
x 12 Listed
Clearance

8'

Minimum

Listed
Vent Cap

Lowest
Discharge
Opening

Listed
Gas
Vent

H (Min.) Height from Roof

Figure 22 - Vertical Vent Termination

Clearance

ROOF PITCH

H(Min.)

Flat to 6/12

1.0'

6/12 to /12

1.25'

Over /12 to 8/12

1.5'

Over 8/12 to 9/12

2.0'

Over 9/12 to 10/12

2.5'

Over 10/12 to 11/12

3.25'

Over 11/12 to 12/12

4.0'

Over 12/12 to 14/12

5.0'

Over 14/12 to 16/12

6.0'

Over 16/12 to 18/12

.0'

Over 18/12 to 20/12

.5'

Over 20/12 to 21/12

8.0'

Figure 21 - Vertical Vent Pipe Offsets

Plumber’s
Tape
Connected
to Wall
Strap

Wall
Strap

Firestop

(2) 45°
Elbows

Firestop

(2) 45°
Elbows

Roof
Flashing

Flat Ceiling Installation

1. Cut a 10

3

/

4

" square hole in the ceiling using

the locating hole as a center point. The open-

ing should be framed to 10

3

/

4

"x10

3

/

4

" inside

dimensions, as shown in Figure 18 on page

13 using framing lumber the same size as the

ceiling joists. If the area above the ceiling is an

insulated ceiling or an attic space, nail firestop

from the top side. This prevents loose insula-

tion from falling into the required clearance

space. If the area above the ceiling is a living

space, install firestop below the framed hole.

The firestop should be installed with no less

than three nails per side (see Figure 23).

Figure 23 - Installing Firestop

If area above is a living space, install
firestop below framed hole.

If area above is an attic, install firestop
above framed hole.