Connecting the Cables

1. Place the cable inlet box-AIB/eAIB gasket around the AIB/eAIB connection panel.

2. Attach the ground lug to the AIB/eAIB. The ground lug is for the cable shield of the

user-supplied 24 VDC cable. See the following figure.

Figure 3-11. Cable Shield Ground Lug Attachment, AIB Shown

3. Hand-tighten all cables to the AIB/eAIB.

NOTE: All cables must be screwed into the AIB/eAIB.

The protective earth ground will be installed in the following section.

Installing the Cable Inlet Box

1. Install the cable inlet box on the top of the AIB/eAIB using three M4 x 40 bolts.

l

Ensure that the gasket is seated between the AIB/eAIB surface and the cable inlet
box.

l

Do not yet use the hole labeled as a ground.

l

Apply Loctite 222 in these bolt holes, not on the bolts themselves.

l

Torque the bolts to 1.1 N·m (10 in-lb).

NOTE: The cable inlet box should be installed with the cables exiting away from
the AIB/eAIB. The cable tray attachment was designed assuming the cables would
exit away from the AIB/eAIB.