FRBH, FRBHX AND FRBHS USER INSTRUCTIONS ENGLISH 71569178 10-04


Page 32 of 54

®

must not limit access or hinder the lifting of the part to
be serviced.

When air or compressed inert gas is used in the
maintenance process, the operator and anyone in the
vicinity must be careful and have the appropriate
protection.

Do not spray air or compressed inert gas on skin.

Do not direct an air or gas jet towards other people.

Never use air or compressed inert gas to clean
clothes.

Before working on the pump, take measures to
prevent an uncontrolled start. Put a warning board on
the starting device with the words:
"Machine under repair: do not start".

With electric drive equipment, lock the main switch
open and withdraw any fuses. Put a warning board on
the fuse box or main switch with the words:
"Machine under repair: do not connect".

Never clean equipment with inflammable solvents or
carbon tetrachloride. Protect yourself against toxic
fumes when using cleaning agents.

6.2 Maintenance schedule

It is recommended that a maintenance plan and

schedule is adopted, in line with these User
Instructions, to include the following:
a) Any auxiliary systems installed must be

monitored, if necessary, to ensure they function
correctly.

b) Gland packings must be adjusted correctly to give

visible leakage and concentric alignment of the
gland follower to prevent excessive temperature
of the packing or follower.

c) Check for any leaks from gaskets and seals. The

correct functioning of the shaft seal must be
checked regularly.

d) Check bearing lubricant level, and if the hours run

show a lubricant change is required.

e) Check that the duty condition is in the safe

operating range for the pump.

f) Check vibration, noise level and surface

temperature at the bearings to confirm satisfactory
operation.

g) Check dirt and dust is removed from areas around

close clearances, bearing housings and motors.

h) Check coupling alignment and re-align if

necessary.

Our specialist service personnel can help with
preventative maintenance records and provide
condition monitoring for temperature and vibration to
identify the onset of potential problems.

If any problems are found the following sequence of
actions should take place:
a) Refer to section 7, Faults; causes and remedies,

for fault diagnosis.

b) Ensure equipment complies with the

recommendations in this manual.

c) Contact Flowserve if the problem persists.

6.2.1 Routine inspection (daily/weekly)

The following checks should be made

and the appropriate action taken to remedy any
deviations:
a) Check operating behaviour. Ensure noise,

vibration and bearing temperatures are normal.

b) Check that there are no abnormal fluid or lubricant

leaks (static and dynamic seals) and that any
sealant systems (if fitted) are full and operating
normally.

c) Check that shaft seal leaks are within acceptable

limits.

d) Check the level and condition of oil lubricant. On

grease lubricated pumps, check running hours
since last recharge of grease or complete grease
change.

e) Check any auxiliary supplies eg heating/cooling (if

fitted) are functioning correctly.

&

Refer to the manuals of any associated

equipment for routine checks needed.

6.2.2 Periodic inspection (six monthly)

a)

Check foundation bolts for security

of attachment and corrosion.

b) Check pump running records for hourly usage to

determine if bearing lubricant requires changing.

c) The coupling should be checked for correct

alignment and worn driving elements.

&

Refer to the manuals of any associated

equipment for periodic checks needed.

6.2 3 Re-lubrication
Lubricant and bearing temperature analysis can be
useful in optimizing lubricant change intervals. In
general however, the following is recommended.