STEP 4.10

STEP 4.12

STEP 5.3

STEP 4.11

STEP 4.9

STEP 4.8 Install a maximum 20-amp circuit breaker(s) into the breaker
panel, depending on the load of the system. Use a 120-VAC single-pole
breaker for a 120-VAC system. Use a 240-VAC double-pole breaker for a
240-VAC system.

For systems that are too large to directly power through one Infloor

Control but must be operated by one floor-sensing control, use a Infloor
Control in combination with up to 10 Infloor Relay Controls . Contact the
dealer or the factory for more information .
STEP 4.9 Cut an opening in the wall for the control electrical box .
If installing one to two cables, use an extra-deep single-gang box to
allow plenty of room for the wiring . Use a 4”-square box if installing
three cables . The box can be located almost anywhere that is well venti-
lated . However, the best place is in the same room as the cable, typically
about 60” above the floor, and within reach of the power lead wires of
the cable . If installing more than three cables, it will be necessary to
connect their power leads in a junction box first (see Step 4 .11) to keep
from overfilling the control box . Then route one power supply from this
junction box to the control box . See Step 5 .22 for special requirements
if the control will connect to a heating cable entering a shower area .
STEP 4.10 Following code, feed 14- or 12-gauge NM type electrical
wiring from the circuit breaker panel to the control electrical box
opening . Leave about 6”–8” of extra wire extended from the opening .
STEP 4.11 If the control box must be mounted in a location that is
too far to reach with the power lead wires, it will also be necessary to
mount a junction box where the lead wires can terminate . Use a
standard junction box with a cover, mounting it below the floor, in
the attic, or in another easily accessible location . It must remain easily
accessible and not located behind a cabinet or similar obstruction . Then
use 14- or 12-gauge NM type or other accepted electrical wiring to con-
nect from the junction box to the control electrical box .
STEP 4.12 At the floor level below the control box, cut a 2”x 2”-wide
piece from the wall surface . Use a wood chisel to notch out a channel in
the baseplate to make it easier to route the wires up the wall .
STEP 4.13 Mark the circuit breaker in the panel which feeds the
system with “Floor warming/bath” or similar .

Phase 5: Install the Cables

Getting Started

IMPORTANT! Refer to Phase 8 and Appendix 1 to make sure the
floor is properly prepared for installation of the cable(s), especially
the use of reinforcement, leveling, and insulation on concrete slab.
STEP 5.1
Use the sketch and design considerations made earlier in

Phase 1 to begin laying the cables . Do not install the cables closer

than about 6” from wax toilet rings and plumbing to keep from over-

heating these items .

STEP 5.2 Make sure to space the cables to provide the warmth

desired . WARNING This heating cable CANNOT be cut shorter to fit! Do

not overlap or cross over heating cable on itself . Do not space heating

cables less than 2” apart . Failure to do so may result in damage to the

product and dangerous overheating .

STEP 5.3 If this is new construction, draw lines on the floor or use tem-

plates to outline the area of any cabinets, fixtures, or future walls that

will be placed in the room . NEVER install the cables under cabinets,

fixtures, or walls . Excess heat may build up under these items and cause

damage .
STEP 5.4 Decide which direc-

tion the cables will run on the

floor for the easiest coverage .

Refer to the sample layouts

in this manual for assistance .

Depending on the shape of the

area, it may help to think of it in
terms of several smaller areas .

NEVER
use 1” spacing

NEVER use less than 2” spacing.

NO!