7 connecting the pv plant – SMA MULTICLUSTER BOX 36 User Manual

Page 29

Advertising
background image

SMA Solar Technology AG

7  Electrical Connection

Operating Manual

MC_BOX_36-BE-en-20

29

13. Connect the neutral conductor to the busbar

MC-X2 (AF 19, torque: 25 Nm). Make sure to
adhere to the following screw assembly:
screw head / terminal of neutral conductor /
terminal lug / fender washer / spring washer / nut.

14. Attach the connection cable to the designated cable support rail. Use the cable clamps and

counter sleeves supplied.
Securing the cable in the support rail relieves the strain on the cable at the connection point.

7.7 Connecting the PV Plant

Cable Dimensioning

Dimension the connection cables adequately for the continuous power of the PV plant and the

short-circuit current of the generator.
In the event of a short circuit, the short-circuit currents released from the generator will flow via the

unprotected connection cable between the Multicluster Box and PV main distribution board. When

planning the short-circuit protection of cables, the PV inverter and Sunny Island inverters may be

disregarded, as their construction precludes any danger to cables in case of short circuits.
Cable requirements:

☐ Conductor material: copper
☐ Maximum conductor cross-section: 300 mm²
☐ Line conductors, neutral conductors and grounding conductors must have the same

cross-section.

Cable protection
The Multicluster Box does not replace the PV main distribution board. Within the PV main

distribution board, you must install circuit breakers to protect and isolate the PV inverters,

and, if necessary, a residual-current device between the Multicluster Box and the PV plant.

Make sure to observe all standards and directives applicable at the installation site.

Connecting other energy generators
Instead of the PV plant, you can also connect other energy generators
(e.g. small wind turbine systems) to the Multicluster Box.