6 Commissioning

6.1 Commissioning the Inverter

1. Check the following requirements before commissioning:

– The inverter is securely in place.
– The AC cables are correctly connected (power distribution grid).
– All DC cables are completely connected (PV strings).
– Unused DC inputs are closed using the corresponding DC connectors and sealing plugs.
– The enclosure lid is securely screwed in place.
– An external DC switch-disconnector is additionally connected or, if available,

the Electronic Solar Switch (ESS) is firmly in place.

– The miniature circuit-breaker is correctly laid out.

2. Switch on the miniature circuit-breaker.

☑ All 3 LEDs are glowing or flashing: the startup phase is starting.
☑ Green LED is glowing: commissioning was successful.
or
☑ Green LED flashes in case of insufficient irradiation: Grid connection conditions have not yet

been reached. Wait for sufficient irradiation.

or
☑ The red or yellow LED is glowing or flashing: a disturbance has occurred. Proceed to step 3.

3. Read section 9 "Troubleshooting" (page 50) and if necessary, eliminate the error or fault.

A

Green LED

Operation

B

Red LED

Ground fault or varistor
defective

C

Yellow LED Fault