Battery Installation

11

2.4.4 MBD voltage sense leads

For ease of installation, the power cables from the battery cabinets can be installed on either the top

or bottom breaker busbars (depending if top or bottom entry is used). The voltage sense leads need to

be connected to the busbars on the input of the circuit breaker (busbars that have the cables from the

battery system connected.) See Figure 22.

2.4.5 Grounding

For cabinets that have been ordered as connected or attached, the ground cables and hardware will be

supplied. See Figure 25 for location of cabinet-to-cabinet grounding.
For cabinets ordered as detached or stand-alone, customer must supply the cables and hardware. See

Table 15 for current ratings and recommended cable sizes.

2.5

Control Connection

Each Liebert NXL Battery Cabinet and Liebert NXL Module Battery Disconnect (MBD) contains a

Battery Interface Board (BIB). See 3.0 - Installation Drawings. All cabinets in a system must have

their Battery Interface boards connected in series. See Figure 14 for battery cabinet details and

Figure 16 for MBD details.

!

WARNING

Risk of electric shock. Can cause equipment damage, personal injury or death.
Hazardous battery voltage may be present on busbar. Install battery voltage sense leads

before connecting the positive and negative power cables.

NOTE
Care must be taken to route the control cables away from high voltage cables or busbars.