8. TEST RUN

8-1. Preparing for Test Run

Before attempting to start the air conditioner, check

the following.

(1) All loose matter is removed from the cabinet especially

steel filings, bits of wire, and clips.

(2) The control wiring is correctly connected and all

electrical connections are tight.

(3) The protective spacers for the compressor used for

transportation have been removed. If not, remove them

now.

(4) The transportation pads for the indoor fan have been

removed. If not, remove them now.

(5) The power has been connected to the unit for at least 5

hours before starting the compressor. The bottom of the

compressor should be warm to the touch and the

crankcase heater around the feet of the compressor

should be hot to the touch.

(Fig. 8-1)

(6) Both the gas and liquid tube service valves are open. If

not, open them now. (Fig. 8-2)

(7) Request that the customer be present for the trial run.

Explain the contents of the instruction manual, then have

the customer actually operate the system.

(8) Be sure to give the instruction manual and warranty

certificate to the customer.

(9) When replacing the control PCB, be sure to make all the

same settings on the new PCB as were in use before

replacement.

The existing EEP ROM is not changed, and is

connected to the new control PCB.

Fig. 8-1

Fig. 8-2

Power mains switch

(Power must be turned ON
at least 5 hours before
attempting test run)

ON

Balance tube

Liquid tube

Gas tube