The anchors must be screwed into

a support capable of bearing the

required static load (generally

rafters or concrete).

Complies with the requirements of

DIN1055.

Roof batten height at least 1".

• The gap between rafter anchor

and top edge of the tile must be at

least 3-5mm. Under no
circumstances may the rafter

anchor be in contact with the tile

(if the overall height of roof batten

and tile do not match, the lower

height must be packed out).

3

Roof Attachment Installation

(continued)

Rafter anchor for roof tiles

#SRM20003 & #SRM20004

The rafter anchor is used for parallel and inclined mounting
on tiled roofs with a roof pitch of at least 15° and an area
loading greater than 6 lb/ft

2

. Can be used for various types

of roofing tiles.

ƽ CAUTION

Figure 3-6 Kit #SRM20003 & #SRM20004 - Rafter
Anchor Kit Components

Unpacking and checking parts

When unpacking the system, check the model names of the
components of each system and check to be sure you have the
correct number of parts (see FIG. 3-6).

RAFTER ANCHOR (1X)

WOOD SCREW (2X)

WASHER (M8) (1X)

HEAVY DUTY WASHER (2X)

HEX BOLT (M8) (1X)

HEX NUT (M8) (1X)

SQUARE DISK (1X)

SPACER PLATE (3X)

Install rafter anchor

1. Determine roof type. Inspect the structural integrity of

the roof and the durability of the roof materials.

2. Determine the number of collectors needed for the

installation and the number of required roof attachments

from Table 3B or 3C on page 11.

3. Determine collector connection points (spacing).

Measure the spacing of the rafters or trusses to confirm

the dimensions and prepare for the system layout

(reference the Roof Attachment Spacing Section on

page

12).

4. Number two (2) tiles, one above the other. The upper

tile will be removed to install the rafter anchor.

5. Mark the edge of the upper tile on the lower tile to

ensure proper alignment upon assembly.

6. Using the rafter anchor as a template, pre-drill two (2)

6 mm holes, approximately 4 inches deep into the roof

substructure (see FIG. 3-7), perpendicular to the roof.

Figure 3-7 Pre-Drill 6mm Holes Into Roof Substructure

USE RAFTER ANCHOR

AS A TEMPLATE

PRE-DRILL TWO (2)

6MM HOLES

APPROX. 4” DEEP

PERPENDICULAR TO

THE ROOF

7. To achieve the recommended 3 - 5 mm clearance above the

tile, place the spacer plate(s) (provided in the kit) between

the rafter anchor and the roof substucture if necessary

(FIG.

3-8).

8. Place the rafter anchor on the spacer plate (if used).

9. Place the heavy duty washers over the holes pre-drilled in
Step

6.

10. Install the wood screws through the washers and rafter

anchor into the roof substructure.

Note: It may be necessary to grind the upper tile to assure a
better fit (FIG. 3-9).