Collector installation, Sch parallel mounting instructions, Ƽ warning – Lochinvar TISUN SCH-I-O User Manual

Page 29: Sch collectors installation & operation manual

Advertising
background image

SCH Collectors Installation & Operation Manual

SCH parallel mounting instructions

4

Collector Installation

(continued)

1. Install roof attachments (see the Roof Attachment

Section on pages 13 - 27 of this manual).

2. Install the horizontal bar(s) (FIG.'s 4-2A and 4-2B)

using the square disk, hex bolt, and washers provided

in the kit.

Figure 4-3 Install Z-Hooks

2 x / per collector

3 x / per collector

SCH065

SCH090, 110, AND 130

INSTALL Z-HOOKS

4. Ensure lifting rings are installed and properly spaced as

per FIG. 4-4.

Figure 4-4 Lifting Rings

< 30°

6.5 ft.

< 30°

6.5 ft.

< 30°

6.5 ft.

< 30°

8.5 ft.

5. Position the collector onto the substructure and hanger

brackets (FIG. 4-5).

Figure 4-5 Position Collector On Substructure

POSITION PANEL ONTO

SUBSTRUCTURE

Z-HOOK

6. Secure the collector to the Z-hook(s) using the

square disk and hex bolt provided in the kit (FIG. 4-6).

SCH Collectors Installation & Operation Manual

Figure 4-2A Install Horizontal Bars

ENDS OF HORIZONTAL BARS

MUST BE PARALLEL TO ENSURE

PROPER COLLECTOR

ORIENTATION

a

a

a

a

=

=

=

55 - 63 in.

a = 2 - 10 in.

x

x

29

Figure 4-2B Spacing

Only loosen the crane connection when
the collectors are completely fixed to the
substructure.

ƽ WARNING

3. Install the Z-hooks per FIG. 4-3 using the

specified number of brackets.

Advertising