UPS SYSTEM INSTALLATION

EATON Powerware

®

9395 UPS (650–825 kVA) Installation and Operation Manual

S 164201725 Rev 2 www.powerware.com

4−7

UPM Wireway

(Power wiring harnesses

are coiled in this area.)

Figure 4-6. ISBM and UPM Sections Joined

10. Reinstall the left top panel (see Figure 4-5) and secure using the retained

hardware.

NOTE Three flat cabinet joining brackets are provided in the hardware kit for securing the ISBM and UPM
sections at the top front, top rear, and front base (see Steps 11 and 12).

11. Locate the hardware kit (packed inside a drawstring bag tied to the left middle

panel of the UPM section). Locate two flat brackets and screws from the
hardware kit. Align the holes in the flat brackets over holes in the top rear and
top front of the ISBM and UPM sections. Secure the brackets with the screws
from the hardware kit (see Figure 4-7).

12. Locate one flat bracket and screws from the hardware kit. Align the holes in the

flat bracket over holes in the front base of the ISBM and UPM sections. Secure
the bracket with the screws from the hardware kit (see Figure 4-7).

13. Proceed to paragraph 4.4.