INSTALLING OPTIONS AND ACCESSORIES

EATON Powerware

®

9395 UPS (650–825 kVA) Installation and Operation Manual

S 164201725 Rev 2 www.powerware.com

5−4

5.2

Installing Distributed Bypass Control Wiring

NOTE When installing external wiring to the Powerware Hot Sync CAN Bridge Card, conduit must be
installed to the UPS cabinet. When installing internal wiring to the Powerware Hot Sync CAN Bridge Card
terminals, route the wiring through the internal opening in the X−Slot communication bay.

NOTE When installing interface wiring for the parallel system pull chain, conduit must be installed
between UPSs.

To install distributed bypass control wiring:

1.

Verify the UPS system is turned off and all power sources are removed. See
Chapter 7, UPS Operating Instructions," for shutdown instructions.

2.

Perform the procedure listed in paragraph 5.1.

3.

Terminal block TB3 is accessible on the left side of the X−Slot communication bay
(see Figure 4-27 on page 4−32). To gain access to terminal block TB1, TB2, and
the left interface entry conduit landing plates, remove the screws securing the
top internal safety shield panel and remove the panel. Retain the hardware for
later use.

4.

Remove the interface entry conduit landing plates to drill or punch holes (see
Figure 4-18 on page 4−20).

5.

Reinstall the interface entry plates and install the conduit.

6.

To locate the appropriate terminals and review the wiring and termination
requirements, see paragraph 3.2.3 on page 3−19, Table 4-1 on page 4−33,

and

Figure 4-27

through Figure 4-30.

7.

Route and install CAN wiring between the UPS cabinets. See Figure 5-2 and
Table 5-1 for the Powerware Hot Sync CAN Bridge Card terminal location and
Figure 5-3, Figure 5-4, and Table 5-2 for wiring information.

8.

If a tie cabinet with Module Output Breakers (MOBs) is being wired, proceed to
Step 11; otherwise, proceed to Step 9.

9.

Route and install distributed bypass system pull−chain wiring between the UPS
cabinets. See Figure 5-5 and Table 5-3 on page 5−6 for wiring information.

10. Proceed to Step 12.

11. Route and install distributed bypass system pull−chain wiring between the UPS

cabinets and tie cabinet MOBs. See Figure 5-6 on page 5−7 and Table 5-4 on
page 5−8 for wiring information.

NOTE Setup of the Powerware Hot Sync CAN Bridge Card for parallel operation must be performed by an
authorized Eaton Customer Service Engineer. Contact an Eaton service representative to schedule a date.

12. Reinstall the top internal safety shield panel and secure with the retained

hardware.

13. Close the door and secure the latch.