INSTALLING THE UPS SIDECAR

EATON Powerware

®

9390 UPS Sidecar Installation and Operation Manual

S 164201586 Rev E www.powerware.com

2-10

2.4.5

Installing UPS Sidecar TB1 Interface Connections

NOTE When installing control wiring (such as Pull Chain and MOB auxiliary contacts) to the UPS Sidecar
interface terminals, conduit must be installed between the the UPS cabinet or device and the UPS Sidecar, if
wiring cannot be run through line-up-and-match cabinets. Install the control wiring in separate conduit from
the power wiring.

1.

Verify the UPS system is turned off and all power sources are removed. Refer to
the applicable Powerware 9390 installation and operation manual, listed in
paragraph 1.5, for shutdown instructions.

2.

If not already removed, remove the screw securing the bottom of the UPS
Sidecar front panel (see Figure 2-1 on page 2-3). Lift up the panel and remove.

3.

If not already removed, remove the screws securing the internal safety shield
panel and remove the panel to gain access to the terminals.

4.

To locate the appropriate terminals, and for wiring and termination requirements,
see Drawing 164201546-7, starting on page A-64, and refer to the applicable
Powerware 9390 installation and operation manual, listed in paragraph 1.5, for
UPS cabinet terminal locations.

5.

Route and connect the MOB monitoring auxiliary contact wiring from the UPS
Sidecar to the UPMs.

6.

Route and connect the CAN and backup control (pull chain) auxiliary contact
wiring from the UPS Sidecar to the UPMs.

7.

When all wiring is complete, reinstall the safety shield panels removed in
previous steps.

8.

Reinstall the UPS Sidecar front panel and secure with screw at the bottom of the
panel.

2.5

Initial Startup

Startup and operational checks must be performed by an authorized Eaton Customer
Service Engineer, or the warranty terms specified on page 5-1 become void. This
service is offered as part of the sales contract for the UPS system. Contact service in
advance (usually a two-week notice is required) to reserve a preferred startup date.

2.6

Completing the Installation Checklist

The final step in installing the UPS Sidecar is completing the following Installation
Checklist. This checklist ensures that you have completely installed all hardware,
cables, and other equipment. Completing all items listed on the checklist will ensure a
smooth installation. Make a copy of the Installation Checklist before filling it out, and
retain the original.

After the installation is complete, a service representative will be able to verify the
operation of the UPS system and commission it to support the critical load. The
service representative cannot perform any installation tasks other than verifying
software and operating setup parameters. Service personnel may request a copy of
the completed Installation Checklist to verify all applicable equipment installations
have been completed.

NOTE The Installation Checklist MUST be completed prior to starting the UPS system for the first time.