6 COMMISSIONING

If any problems or malfunctions occur during the commissioning, refer to the chapter “Troubleshooting” to find out
the reason. The source of any problems with the product must be solved before continuing with the commissioning
procedure.

WARNING

To avoid electrical shock, ensure that the main isolation switch is turned to the
off position before connecting the frequency converter to the mains supply.

WARNING

To avoid damage to the equipment or persons, ensure the proper mounting of
the motor before starting. Also, make sure that the machinery connected to the
motor allows the motor to run.

6.1

Visual checks

1

Check that the main power is switched off.

2

Check that the serial number of the drive is the same as in
the delivery documents.

3

Check the connections and condition of cabling to motor,
braking resistor (not in 003), grounding, and thermistors.

4

Check the motor type, nominal voltage, nominal current and
nominal frequency.