5 restore to normal operation after “total off, Restore to normal operation after “total off – GE Industrial Solutions LP 33U Series 10 & 20 kVA Operating Manual User Manual

Page 47

Advertising
background image

Modifications reserved

Page 47/63

OPM_LPS_3UO_10K_20K_1US_V010.doc

Operating Manual LP 33U Series 10 & 20 kVA / S1

7.1.5 Restore to normal operation after “Total Off”

NOTE !

Make sure the UPS to be status of the activation of “Total Off”, i. e. Q1 closed, Q2
open and the “Rectifier input fuses - F1, F2, F3”
and “Battery fuses - F9, F10, F11 / F13,
F14, F15”
connected.






View of the synoptic diagram after pressing the “Total Off” key:
All Contactors are open.
Booster, Inverter and Static-Switch shutdown.






`

Home\Commands

COMMANDS

RESET TOTAL OFF


REQUEST TOTAL OFF


1. Reset

Total Off”.

Restore the command “Total Off” by entering the screen:
COMMANDS / RESET TOTAL OFF


LED Alarm is lit.

V



The load is supplied by the utility through the automatic
bypass
.
The booster starts automatically.
The synoptic diagram must display the statusLOAD
SUPPLIED BY AUTOMATIC BYPASS
.

2. Insert the inverter by pressing Inverter ON ( I ) key.

Some seconds later the load will be transferred on inverter.
LED Alarm turn Off and the LED Operation must be lit.
The synoptic diagram must display the statusLOAD
SUPPLIED BY INVERTER
.

END OF PROCEDURE