7 restore to normal operation after “total off, Restore to normal operation after “total off – GE Industrial Solutions LP 33U Series 10 & 20 kVA Operating Manual User Manual

Page 59

Advertising
background image

Modifications reserved

Page 59/63

OPM_LPS_3UO_10K_20K_1US_V010.doc

Operating Manual LP 33U Series 10 & 20 kVA / S1

7.2.7 Restore to normal operation after “Total Off”

NOTE !

Make sure the all units of the Parallel System to be status of the activation of “Total
Off”
, i. e. Q1 closed, Q2 open and the “Rectifier input fuses - F1, F2, F3” and “Battery
fuses - F9, F10, F11 / F13, F14, F15”
connected.



View of the synoptic diagram, on all UPS units, after pressing
the “Total Off” key
.

All Contactors are open.

Booster, Inverter and Static-Switch shutdown.




`

Home\Commands

COMMANDS

RESET TOTAL OFF


REQUEST TOTAL OFF


1. Reset

Total Off” of the Parallel System.

Restore the command “Total Off”, on anyone of the parallel units, by
entering the screen:
COMMANDS / RESET TOTAL OFF


LED Alarm is lit.

V



The load is supplied by the utility through the automatic bypass.
The booster starts automatically.

The synoptic diagram, on all UPS units, must display the status

LOAD SUPPLIED BY AUTOMATIC BYPASS.

2. Insert the inverter by pressing Inverter ON ( I ) key on first UPS unit.

In case of sufficient output power, the output will transfer to

Inverter.
LED Alarm turn Off and the LED Operation must be is lit.
The synoptic diagram, on first UPS unit, must display the status

LOAD SUPPLIED BY INVERTER.

3. Insert the inverter by pressing Inverter ON ( I ) key on all other UPS units.

Do not start the next inverter until the sequence of the previous one end.
As soon as the output power of the inverters is sufficient to supply the load, the output of the units with

running inverter will transfer to inverter.

LED Alarm turn Off and the LED Operation must be lit.

The synoptic diagram, on all UPS units, must display the status

LOAD SUPPLIED BY INVERTER.

END OF PROCEDURE

Advertising