e)

Resources to support the use and maintenance of the product during the
design phase.

Output from this planning is in a form suitable for FCI‟s method of
operations and may be (but is not limited to) the following:

Quality System Procedures and/or Documentation

MRP Data

Delivery Method Information

Quality Objectives

Organizational Infrastructure

Department Specific Documentation

Product Realization Documentation

7.1.1 PROJECT MANAGEMENT

As appropriate to FCI and the product, FCI shall plan and manage product
realization in a structured and controlled manner to meet requirements at
acceptable risk, within resource and schedule constraints.

7.1.2 RISK MANAGEMENT

FCI shall establish, implement and maintain a process for managing risk to the
achievement of applicable requirements, that includes as appropriate to the
organization and the product

a)

Assignment of responsibilities for risk management,

b)

Definition of risk criteria (e.g. , likelihood, consequences, risk
acceptance),

c)

Identification, assessment and communication of risks throughout product
realization,

d)

Identification, implementation and management of actions to mitigate
risks that exceed the defined risk acceptance criteria, and

e)

Acceptance of risks remaining after implementation of mitigating actions.

7.1.3 CONFIGURATION MANAGEMENT

The organization shall establish, implement and maintain a configuration
management process that includes, as appropriate to the product