DOOR INSTALLATION

MOUNTING THE DOOR

Hang each door panel onto the roller bracket studs and secure with two M8 nuts; the nuts
should only be finger tight to allow height and leveling adjustment. Be sure that the rear
flange of the door hanger bracket is positioned on top of the leveling nuts, see second
picture below.

Adjust leveling nuts as required to level each door assembly. The leveling nuts include
nylon inserts to prevent rotation during use. Do not overtighten. Once both door
assemblies are leveled, tighted the M8 nuts attaching the door assembly to the bracket
finger tight then 1/4 turn with a wrench.