Chatsworth Products Hot Aisle Containment User Manual

Page 6

Advertising
background image

BTS Aisle Containment Manual, Rev. 1.0

___

December 2013

Chatsworth Products

6

TOOLS REQUIRED FOR ASSEMBLY AND INSTALLATION

The following tools are required to assemble the Build To Spec Kit and Aisle Containment
Doors. Additional tools may be required depending on site-specific requirements.

Tool

Application

Mitre saw with metal/aluminum cutting blade

For cutting frame components

Jig/reciprocating saw with metal cutting blade For cutting corner brackets
Utility Knife or Flute Cutter

For cutting poly panels/bulb seal

Straight edge or Guardian Knife Guide*

For cutting poly panels/bulb seal

#2 Phillips screwdriver or bit for drill/driver

Assembly, BTS Kit

#3 Phillips screwdriver or bit for drill/driver

Assembly, Door

8 mm socket and open end wrench

Assembly, Door

10 mm socket and open end wrench

Assembly, Door

13 mm socket and open end wrench

Assembly, Door

Ladders

Installation

Levels

Installation

Drill, bits

Installation

*For best results when cutting corrugated plastic sheet use specialized cutting tools, like
the Guardian Knife Guide by Saw Trax Mfg. Inc.

SITE PREPARATION

Floor
In an access floor installation, ensure that the floor is strong enough to support the fully
populated computer cabinets, and the additional weight of the Build To Spec Kit (aisle
containment duct) and Aisle Containment Door Systems. If required, add subfloor
bracing to provide the proper support for equipment.

Subfloor bracing.

Ceiling
If supporting from threaded rod, ensure that the ceiling is strong enough to support the
Build To Spec Kit (aisle containment duct). Threaded rod used to support the duct
should only be used to support the duct.