Brocade MLX Series and Brocade NetIron XMR Hardware Installation Guide

261

53-1002373-02

Installing a Brocade NetIron XMR 8000 router

4

CAUTION

To ensure adequate bonding when attaching the ground lug, a minimum of 20 PSI of torque is
required to be applied to the mounting hardware used to attach the ground lug.

FIGURE 183

Crimping the power supply wire in the lug

5. Connect the -48V cable to the negative terminal and the 0V cable to the positive terminal as

marked on the power supply.

NOTE

DC return must be isolated from the device ground (DC-I) when connecting to the power supply.

6. Replace the transparent cover.

This equipment installation must meet NEC/CEC code requirements. Consult local authorities for
regulations.

Final steps

Follow these steps to complete the installation:

“Attaching a management station”

“Activating the power source”

“Verifying proper operation”

1

AWG power supply wire:
#8 AWG wire for 1200 W power supply
#6 AWG wire for 1800 W power supply