Construction

This application allows to define
a construction site by combining
set-up of the instrument along a
construction line and measuring
in relation to the line.

Procedure:
Line Start point

[MEAS]

Measures to point

[COORD]* Entry of point

coordinates

Second Line point

[MEAS]

Measures to point

[COORD]* Entry of point

coordinates

*

)

Visible if [SHIFT] is pressed

In case, you have
entered coordinates by

[COORD] and measured to
known points a plausibility
check informs you about the
calculated line length, the actual
length and the difference.

This dialog shows you the

S

Line,

S

Offset and

S

Height of a

measured point in relation to the
line.

NORTH is positive:
Measured point is in direction
from line start - to line end point.

EAST is positive:
Measured point is right of line.

S

S

S

S

S

Height is positive:

Measured point height is above
line start point's height.

As built check

TPS100z96

The height of the line
start point is always

used as the reference height!

1) Line Start point
2) Second Line point
3) North
4) East