Warning, Heating element and air channel installation – Steffes 5140 Owner & Installers Manual User Manual

Page 13

Advertising
background image

HeatinG eleMent anD air cHannel inStallation

Step 1 After all brick are loaded, insert the heating elements

between the brick layers, sliding them in until the element

ends embed into the side cutouts of the brick cavity. Ele-

ments MUST be installed with the threaded screw tabs on

the wire connection terminals pointing forward and down

to ease the installation of the element-to-wiring harness.

Note the required clearance (Figure 6.)

Step 2 Install the front air channel by placing the bottom in first,

with the air deflectors (arrow shaped pieces) facing inward.

Refer to the Air Channel Placement (Figure 7) and the

Parts Diagram (Page A.02) for proper placement and instal-

lation of the front air channel.

Step 3 Lower the insulation blankets back into position, one at a

time. Carefully tuck the sides of this insulation into the edges, corners, and around the exposed portions of

the heating element to ensure maximum efficiency.

Step 4 Reinstall the galvanized

front panel by sliding

the bottom of the panel

inside the lower lip of

the brick cavity and

resting the top of the

panel on the outside of

the brick cavity. Secure

it to the Comfort Plus

Hydronic system using

the screws that were

originally removed.

Step 5 Remove the painted

front panel of the

electrical compartment

by removing the screws

along the edges. Locate the installation hardware package that is shipped in this compartment.

Step 6 Carefully route the element wiring harnesses and connect them to the heating elements, using the screws

provided in the hardware package. Connections should be made with the screw heads up and the threads

pointing down. Element screws should be tightened to 30 inch lbs. Refer to Figure 6 for proper positioning.

Installation

3.03

Comfort Plus Hydronic

Comfort Plus Hydronic

Installation

3.04

HAZARDOUS VOLTAGE: Risk of elec-

tric shock. Can cause injury or death.

DO NOT remove the electrical panel

cover while system is energized.

Position elements properly to avoid

short circuiting them against metal

surfaces.

Protect element lead wires from

front panel screws and any field in-

stalled screws to avoid short circuit.

WARNING

FIgUrE 4

FIgUrE 5

i.e.: Rows 2, 4, 6, 8, 10 and 12 in 5140

Front

Indicator

5120 - load in row 5

5130 - load in row 4 and 8

5140 - load in row 6 and 12

Half Brick

Forward Facing Indicator

rear Facing Indicator

Half Brick

Indicator in Brick

3

4"

required Clearance Between

Element Termination and Metal

Panels is 1/2" (3/4" Nominal)

Element Connection

ElEMENT INSTAllATION

FIgUrE 6

TOP

AIr CHANNEl PlACEMENT

FIgUrE 7

Electrical

Panel

Front Air

Channel

BrICK

COrE

SIDE VIEW

Outlet

Inlet

Advertising