Step 4 Press the up arrow again and the current heat call status will be displayed on the

control panel. Refer to the Operating Status section (Page 1.02) for more information

on the heat call status display.

Step 5 Initiate a heat call from each room thermostat (one at a time) and verify that the Comfort Plus Hydronic

system recognizes the appropriate heat call. Refer to the Operating Status section (Page 1.02) for

information on the various heat call status displays. In applications utilizing the Air Handler, verify that

the Air Handler and/or heat pump operates appropriately.

Step 6 If utilizing the Air Handler, initiate a cooling call from the room thermostat and verify that the Comfort

Plus Hydronic system recognizes the “COOL” call. Verify that the Air Handler, heat pump, and/or air

conditioner operates appropriately.

Step 7 Press the up arrow until the targeted brick core charge level is displayed on the control

panel. With the system in an off-peak (charge) mode, initiate the charge control

override. Refer to the Charge Control Override section (Page 1.03) for instructions on

initiating the charge control override. Once initiated, the target level of the Comfort

Plus Hydronic should be 100 percent, the control panel should display “tL: F”, and all of the heating

elements should be energized.

Step 8 With an amp meter, verify that the amperage of the system is correct for the installation. Refer to the

System Identification Label on the Comfort Plus Hydronic system for information regarding the proper

amperage.

Step 9 Cancel the charge control override and verify that all elements in the system de-energize. Refer to the

Charge Control Override section (Page 1.03) for instructions on canceling the charge control override.

Step 10 Verify that all hydronic heating zones are operating as intended.
Step 11 Verify, once again, that the “Operating Mode” displayed on the control panel corresponds with the power

company's peak control signal.

Step 12 In applications utilizing the Steffes Power Line Carrier control system, complete the Installer’s Final

Check-out Procedure in the Owner’s and Installer’s Manual provided with that device.

Step 13 Complete the manufacturer's warranty card and return promptly.

inStaller'S final cHeck-out ProceDure

Step 1 Verify that the water pressure is correct for the application. The

water pressure of the Comfort Plus Hydronic heating system should

be between 12 and 20 psig.

Step 2 Verify that the operating mode displayed on

the control panel corresponds with the power

company's peak control signal. Refer to the

Operating Status section (Page 1.02) for more

information on the proper operating mode.

Step 3 Press the up arrow one time and verify that the

outdoor temperature information displayed on the

control panel is approximately the same as the

current outdoor temperature. Refer to the Operating

Status section (Page 1.02) for more information on the outdoor

temperature display.

HAZARDOUS VOLTAGE:

Risk of electric shock.

Can cause injury or death.

System may be connected

to more than one branch

circuit. Disconnect power

to all circuits before ser-

vicing. Equipment must

be serviced by a qualified

technician.

WARNING