LAARS Sequencing Controls S8 & S8EXT

LEAD BOILER

Depending on the number of stages

Default: The first set of stages

Button: MENU/<System Settings>/<Stage Settings>/<Lead Setting>/Rotate Mode

• The Lead Unit’s lowest stage will always be the first stage brought on when there is a

call for output. As more output is needed, additional Stages are added.

• The Lead Unit is always shown on the main display in brackets.

• In a 2-Stage system (see Boiler Type in the Startup section), the display will show the

No Pump or Valve stages

-- LEAD BOILER --

BACK SELECT

two Lead Unit stages bracketed <AB>. In a 3-Stage system, the display will show the

three Lead Unit stages bracketed <ABC>, and so on.

• If Pump or Valve is selected as the Boiler Output in the Startup menu, the Valve or Pump

letter will be skipped from the number of stages. See example to the right. The missing

stage C and F represent the Unit Valve or Pump.

• The Lead Unit can be rotated based on the Rotation Mode selected. (See next setting)

with Pump or Valve stages

-- LEAD BOILER --

AB

DE

BACK SELECT

ROTATE MODE

Adjustable Time (1 hr to 999 hrs), Manual, FOFO

Default: Time (24Hours)

Button: MENU/<System Settings>/<Stage Settings>/<Lead Setting>/Rotate Mode

• The Lead Unit is the first unit brought on when output is required.

• The Lead Unit can be rotated automatically, manually or based on First-On/First-Off

(FOFO). The automatic rotation is recommended for most applications.

• The current Lead Unit is shown in brackets on the main display.

• Only units which are set to Auto Mode can be Lead. Therefore, not all the units may be

available when manually selecting a new Lead Unit.

• If Time is selected, a second screen will allow the adjustment of the Auto Rotate Period

If 24 Hours (default setting) was selected, the first rotation will take effect after 12 hours

if the Time was not set. However, if the Time was set, the rotation will always take

place at 2:00AM. The following rotations will take place every 24 hours thereafter.

• If First-On/First-Off (FOFO) is selected, the concept will follow this example; If A is the

Lead, the starting sequence will be A, B, then C. When the de-energizing of the stages

starts it will turn off A, B, Then C. Then stage D will be the new lead for the next load.

SETBACK SCHEDULE

Button: MENU/<System Settings>/<Stage Settings>/<Setback Schedule>

This menu provide the Day/Night Schedule as well as the Setback and Boost settings.

-- LEAD ROTATION --

Time

Manual

FOFO

BACK SELECT

If Time Rotation is selected

AUTO ROTATE PERIOD

24hrs

[ ]

BACK SAVE

SETBACK SCHEDULE

Setback

0 F

Present Time **:**

Day Schdule 7:00Am

Night Schdul

7:00Pm

BACK SELECT

SETBACK

Adjustable 0°F/0°C to 80°F/44°C

Default: 0°F/0°C

Button: MENU/<System Settings>/<Setback Schedule>/Setback in Day/Night Schedule

Button: MENU/<System Settings>/Setback

in External Signal

• The Setback feature can be used to provide the S8 with a lower temperature Set Point in

Heating or a higher Set Point in Cooling when less load is required.

------ SETBACK -------

0 F

[ ]

BACK SAVE

• For example, if in heating the calculated temperature is 180°F and the Setback is 20°F, then when in Setback, the S8 will hold a

Set Point of 160°F. The new Set Point will appear on the main display indicating this condition "Setback to 160 F".

• A typical use for Setback is to provide less system temperature in heating to a building during the night or on the weekends

when building is not occupied, but heat is still required.

• After selecting a value in Setback, you'll be directed to the Boost menu.

BOOST

Adjustable 0°F/0°C to 80°F/44°C

Default: 0°F/0°C

Button: MENU/<System Settings>/Setback/Boost

• This features allows a building to either warm up or cool down quickly after a Setback

period to bring the building to the desired temperature faster.

-------- BOOST ---------

0 F

[ ]

BACK SAVE

• The Boost temperature will be the number of degrees to be added in Heating or subtracted in Cooling from the Calculated

Target Temperature.

• Using the previous example, if the Target was 180°F and the Setback was 20°F and the Boost was 10°F for 30 minutes, after the

setback period, the Boost will change the target to 190°F for a period of 30 minutes. The new Set Point will appear on the main

display indicating this condition "Boost to 190 F".