Warning, Notice – Proheat M125 User Manual

Page 51

Advertising
background image

e)

Using a flat head screwdriver hold the valve stem while loosening the coil

nut. Remove the coil.

r)

Loosen and remove the valve stem. Remove the O-ring, plunger and

spring. Save the parts.

g)

Inspect the O-ring and plunger seat for contamination. Clean as

necessary using electrical contact cleaner. Reinstall the valve stem and

O-ring using diesel fuel to lubricate O-ring. DO NOT INSTALL THE

PLUNGER AND SPRING.

h)

Reinstall the coil, coil nut and reconnect the Fuel Solenoid Valve to the

G-II PCM.

i)

Reinstall the burner head by mounting it against the heat exchanger face,

turning clockwise to engage the mounting ears on the bolts.

j)

Reconnect electrical harnesses and fuel supply line.

k)

Switch the PROHEAT on and operate for at least one complete cycle.

Observe the operation.

If the PROHEAT runs OK, the Fuel Solenoid Valve is faulty. Go to Fuel

Solenoid Valve replacement.

If a Start diagnostic code is indicated, proceed to Step 6.

Fuel Solenoid Valve replacement:

a)

Using a flat head screwdriver, hold the stem in place while loosening the

coil nut. Remove the coil.

b)

Loosen and remove the valve stem. Remove the O-ring, plunger and spring.

c)

Inspect the O-ring and plunger seat in the fuel block for contamination.

Clean as necessary using plastic safe electrical contact cleaner.

d)

Install the new valve stem (with plunger) and seal using a slot screwdriver.

e)

Reinstall the coil, coil nut and reconnect the Fuel Solenoid Valve connector

at the G-II PCM.

f)

Reinstall the burner head by mounting it against the heat exchanger face,

turning clockwise to engage the mounting ears on the bolts.

g)

Reinstall electrical harnesses and fuel supply line.

h)

Switch the PROHEAT on and operate for at least one complete cycle.

Observe the operation.

WARNING

Spilt fuel is flammable.

WARNING

The fuel flow will not be shut off during

cool down (purge). The G-II PCM will

see the flame in cool down (purge)

and after 20 seconds the G-II PCM

will turn off the motor to stop the

flow of fuel and extinguish the flame.

The hot combustion gases can cause

damage to the heater if this test is

preformed repeatedly.

Figure 4-15: Fuel Solenoid Valve Assembly.

COIL

PLUNGER

STEM
TORQUE = 25 in-lbs

±

3 in-lbs (3.4 Nm

±

0.3 Nm)

COIL NUT
TORQUE = 25 in-lbs

±

3 in-lbs (3.4 Nm

±

0.3 Nm)

SCREWDRIVER SLOT
TORQUE = 25 in-lbs

±

3 in-lbs (3.4 Nm

±

0.3 Nm)

NOTICE

All plugs/harnesses must be rein-

stalled into the G-II Proheat Control

Module (G-II PCM) before heater

goes back into service.

O-RING

4-14

PROHEAT M-SERIES G-II PCM SERVICE MANUAL

Advertising
This manual is related to the following products: