Electrical Connection

SMA Solar Technology AG

42

WB5A_6A-IA-IEN114540

Installation Manual

Procedure

1. Open the inverter as described in Section 7.2 "Opening the Inverter" (page 57).
2. Insert the cable into each inverter.

Use one of the two enclosure openings (F) on the bottom right hand side.

3. Lead the cable along the cable route (E) as far as the terminal block (B).
4. Ground the cable shield in each inverter at the PE terminal (D).
5. Sheath the positive and negative cable conductors in each inverter with end sleeves.
6. Connect the positive and negative pole to the

corresponding screw terminals.

7. To connect the 3 inverters, connect the positive and negative cables from the 2 other inverters

to the terminal block of the middle inverter.

The length of the cables between 2 inverters must not exceed 300 m.

DANGER!
Danger to life due to high voltages on the SMA Power Balancer cable when
faults occur

• Sheath the positive and negative cable conductors in each inverter using the silicone

tube provided.

• Cut the silicone tube to the required length.
• The silicone tube must completely protect the cable inside the inverter.