Installation Checklist

32

3.0

I

NSTALLATION

C

HECKLIST

___ 1. Unpack and check received material.
___ 2. Position Liebert XDC and secure to floor.
___ 3. Wire high voltage connections.
___ 4. Wire low voltage connections.
___ 5. Connect Liebert XD cooling module piping to Liebert XDC.
___ 6. Check all circuits of the system for leaks.
___ 7. Hold a vacuum on all circuits of the system.
___ 8. Charge the system with refrigerant.
___ 9. Make sure that all piping has proper insulation.
___ 10. Use double risers in DX hot gas lines that are 15 feet (4.6m) or more in height.