– 40 –

Closed completely

9-8-3. Heat insulation

1. Provide heat insulation on the refrigerant piping on

both the liquid side and gas side separately, and
ensure that all joints in the insulation are completely
sealed (without gap).

2. Since the temperature of the piping on the gas side

increases during heating operations, the heat
insulating material used must be able to withstand
temperatures of more than 120

°

C.

3. Use the pipe insulation supplied in the accessory

pack to insulate the piping connecting section on
the indoor unit side.

Fig. 9-8-1

<For RAV-SM800AT-E model>

As shown in the figure, be sure to use a double
spanner to loosen or tighten the flare nut of the
valve at gas side. If using a single spanner, the nut
cannot be tightened with necessary tightening
torque.

SM800 type valve at gas side

Fig. 9-8-2

Gas side (12.7 mm (diam.))

50 to 62 N•m (5.0 to 6.2 kgf•m)

Liquid side (9.52 mm (diam.))

33 to 42 N•m (3.3 to 4.2 kgf•m)

Liquid side (6.35 mm (diam.))

14 to 18 N•m (1.4 to 1.8 kgf•m)

Service port

14 to 18 N•m (1.4 to 1.8 kgf•m)

Flare nut

Cover

Cap

Piping valve

Loosened

Tightened

Cover

Do not put the spanner or
torque wrench, etc. on the
cover.
The valve may be broken.

Hexagonal wrench is required.

9-8-4. Packed valve handling precautions

Open the valve stem all the way out; do not try to
open it beyond the stopper.

Securely tighten the valve stem cap in torque as
follows:

Valve unit

Charge port

Push in handle.

Opened fully

Handle

Valve unit

Handle
Pull out the handle and
using cutting pliers, etc.
turn it counterclockwise
by 90°. (Open fully)

Charge port

Flare nut

Flare nut

Fig. 9-8-3

On the contrary, use a single spanner to loosen or
tighten the flare nut of the valve at liquid side.

Fig. 9-8-4

Fig. 9-8-5

Fig. 9-8-6