MARK 3 USER INSTRUCTIONS ENGLISH 71569102 08-06

Page 21 of 68

flowserve.com

f)

After leveling the baseplate, tighten the anchor

bolts. If shims were used, make sure that the

baseplate was shimmed near each anchor bolt

before tightening. Failure to do this may result in

a twist of the baseplate, which could make it

impossible to obtain final alignment.

g) Check the level of the baseplate to make sure

that tightening the anchor bolts did not disturb

the level of the baseplate. If the anchor bolts did

change the level, adjust the jackscrews or shims

as needed to level the baseplate.

h) Continue adjusting the jackscrews or shims and

tightening the anchor bolts until the baseplate is

level.

i)

Check initial alignment. If the pump and motor

were removed from the baseplate proceed with

step j) first, then the pump and motor should be

reinstalled onto the baseplate using Flowserve’s

factory preliminary alignment procedure as

described in section 4.5, and then continue with

the following. As described above, pumps are

given a preliminary alignment at the factory. This

preliminary alignment is done in a way that

ensures that, if the installer duplicates the factory

conditions, there will be sufficient clearance

between the motor hold down bolts and motor foot

holes to move the motor into final alignment. If the

pump and motor were properly reinstalled to the

baseplate or if they were not removed from the

baseplate and there has been no transit damage,

and also if the above steps where done properly,

the pump and driver should be within 0.38 mm

(0.015 in.) FIM (Full Indicator Movement) parallel,

and 0.0025 mm/mm (0.0025 in./in.) FIM angular. If

this is not the case, first check to see if the driver

mounting fasteners are centered in the driver feet

holes. If not, re-center the fasteners and perform a

preliminary alignment to the above tolerances by

shimming under the motor for vertical alignment,

and by moving the pump for horizontal alignment.

j)

Grout the baseplate. A non-shrinking grout

should be used. Make sure that the grout fills

the area under the baseplate. After the grout

has cured, check for voids and repair them.

Jackscrews, shims and wedges should be

removed from under the baseplate at this time.

If they were to be left in place, they could rust,

swell, and cause distortion in the baseplate.

k) Run piping to the suction and discharge of the

pump. There should be no piping loads

transmitted to the pump after connection is

made. Recheck the alignment to verify that

there are no significant loads.

4.5 Initial alignment

4.5.1 Horizontal initial alignment procedure

The purpose of factory alignment is to ensure that the

user will have full utilization of the clearance in the

motor holes for final job-site alignment. To achieve

this, the factory alignment procedure specifies that

the pump be aligned in the horizontal plane to the

motor, with the motor foot bolts centered in the motor

holes. This procedure ensures that there is sufficient

clearance in the motor holes for the customer to field

align the motor to the pump, to zero tolerance. This

philosophy requires that the customer be able to

place the base in the same condition as the factory.

Thus the factory alignment will be done with the base

sitting in an unrestrained condition on a flat and level

surface. This standard also emphasizes the need to

ensure the shaft spacing is adequate to accept the

specified coupling spacer.

The factory alignment procedure is summarized

below:

a) The baseplate is placed on a flat and level

workbench in a free and unstressed position.

b) The baseplate is leveled as necessary. Leveling

is accomplished by placing shims under the rails

of the base at the appropriate anchor bolt hole

locations. Levelness is checked in both the

longitudinal and lateral directions.

c) The motor and appropriate motor mounting

hardware is placed on the baseplate and the motor

is checked for any planar soft-foot condition. If any

is present it is eliminated by shimming.

d) The motor feet holes are centered on the motor

mounting fasteners. This is done by using a

centering nut as shown in figure 4-6.

Figure 4-6

e) The motor is fastened in place by tightening the

nuts on two diagonal motor mounting studs.

f) The pump is put onto the baseplate and leveled.

The foot piece under the bearing housing is

adjustable. It is used to level the pump, if necessary.

Mark 3A and ANSI 3A design

If an adjustment is necessary, add or remove

shims [3126.1] between the foot piece and the

bearing housing.