Figure #52, Transition installation (tr-4734), As viewed from inside bin – Grain Systems PNEG-366 User Manual

Page 44

Advertising
background image

Grain Systems, Inc. Assumption, Ill.

44

18' Autoflow

REV. 11-20-96

Figure #52

Note: Entrance collar side

bracket (TR-4731) flange

must be installed to the

inside of the bin sidewall.

TRANSITION INSTALLATION (TR-4734)

BEFORE CUTTING THE OPENING CHECK THAT TR-4734 IS THE TRANSITION THAT WAS

ORDERED.

When installing the GSI aeration transition, it will be necessary to field cut a hole into the bottom sidewall ring

(usually straight across from the unload auger). Refer to diagram for proper dimensions of cutout. The base

angle will also need to be cut at entrance collar cutout. Take note of the diagram showing the 1" dimension

from bottom of entrance collar side bracket to concrete. This is important for proper fit of transition.

NOTE: Entrance collar side bracket must be bolted on the inside of the bin sidewall.

AS VIEWED FROM INSIDE BIN

Part No.

Description

Quantity

S-275

5/16" - 18 3/4" Bin Bolt Grade 5

125

S-280

#10 - 16 x 5/8" Self Drill Screw

10

CH-6873

Tube Caulk - Silicone

1

S-396

5/16" - 18 Hex Nut Grade 2

125

S-7264

Spec Neoprene Seal Strip W/ADH

10 Ft

Advertising