Gradall – Gradall 544D (9136-4003) Service Manual User Manual

Page 307

Advertising
background image

3.1

A

DJUSTING

S

IDE

P

LATE

B

EARING

P

ADS

Preparation

Extend the boom 60%.

Lower the boom approximately I foot off the ground for easy accessibility.

Force the boom section being checked to the opposite side to achieve maximum gap

between bearing pad and side plate.

Note! If a wedge is used, do not distort the side plate.

Using 1/16" shim stock as a feeler gauge, check the gap between the boom side plate

and the pad.

If shim stock will not fit in the gap, the pad needs no adjustment.

If shim stock penetrates the gap, the pad needs adjustment.

Adjustment

Loosen the bearing pad mounting bolts on the pad and the pad on the opposite side

of the boom.

Select the correct size shims to bring the boom back into 1/16" tolerance.

Install shims Note! Keep shim packs equal. There should be no more than 1 shim

variance from the opposite side.

Re-torque the mounting pad bolts as required (using LOCTITE 242 per standard

Gradall recommendations).

A

DJUSTING

B

OTTOM

B

EARING

P

ADS

Lower the boom to the ground, applying minimum down pressure sufficient to raise the

boom sections against the top bearing pads.

Using 1/16" shim stock as a feeler gauge, check the clearance between the bottom pads

and the bottom plate.

If shim stock will not fit in the gap, the pad needs no adjustment.

If shim stock penetrates the gap, the pad needs adjustment.

Adjust pads by loosening the mounting bolts, installing the correct shims cind re-torqueing

the mounting bolts (using LOCTITE 242 per standard Grodall recommendations).

A

DJUSTING

T

OP

B

EARING

P

ADS

Check

The top bearing pads rarely require adjustment. However, should adjustment become necessary:

Level the boom assembly.

Retract the boom assembly half-way.

Using 1/16" shim stock as a feeler gauge, check the clearance between the top pad and

the top boom plate.

Adjustment: If Clearance is Excessive

Determine the amount of shim stock required.

Remove the shim pack from the bearing pads on the opposite bottom.

Apply minimal down pressure to the boom sufficient to force the bearing pad

away from the inside top of the next outer boom.

Loosen the bolts on the bearing pads requiring adjustment, install a shim and re-torque

the bolts (using LOCTITE 242 per standard Gradall recommendations).

Re-shim the bottom bearing pads per instructions above, “Adjusting Bottom

Bearing Pads.”

1.

2.

3.

4.

5.

6.

1.

2.

3.

4.

1.

2.

3.

4.

5.

1.

2.

3.

1.

2.

3.

4.

5.

Note!

You may have to odd an extension

to the shim stock in order to access

some bearing pads.

GRADALL

GRADALL

Advertising