Electrical installation
Preparations
Integrated PE conductor connection
l
101
EDS700ACBA EN 4.0
6.5
Preparations
When the mechanical installation has been completed, the electrical wiring starts with the
creation of the integrated electrical connections:
6.5.1
Integrated PE conductor connection
How to proceed:
ƒ
Use the swivel hook to establish the PE conductor connection of the devices.
– Loosen the screws
– Turn the swivel hook into the right position
– Fasten the screws
ƒ
At the left and right device of an installation row, attach the PE connection twice
conforming to standards.
ƒ
Then attach the shield connection sheet.
i700A00x
Terminal data
Conductor cross−section
Tightening torque
!
[mm
2
]
[AWG]
[Nm]
[lb−in]
Swivel hook
+
−
−
2.5
22.1
PH 2