About This Chapter

This chapter describes how to set up and run the Example HCF Test using a typical MTS TestLine system.

Adapting This Chapter to Your System

The system shown in this chapter uses typical TestLine components. This procedure is intended to be an
example that shows the details involved with running a common test. Because it is likely that your system
varies from the typical system shown, you will need to adapt the concepts shown. In addition, the values
provided will also likely need to be adapted to your particular system. If you have questions regarding how
to do this, call MTS Technical Support for assistance.

Test Procedure Overview

The following is an abbreviated version of the complete Example HCF Force Test procedure.

1.

Station Equipment Checkup

2.

Install the Specimen

(p. 78)

3.

Prepare To Run Test

(p. 84)

4.

Run the Example HCF Test

(p. 103)

5.

Remove the Specimen

(p. 111)

6.

If Necessary, Recover from a Tripped Displacement Limit

(p. 113)

Station Equipment Checkup

Checking your equipment helps ensure that your system is ready to collect valid data.

Turn on the Controls

1. Turn on the computer.

2. Turn on the controller.

50 | MTS TestLine Test System Operation

Running the Example HCF Test

Advertising