Verify That the System Is Ready for Use
Before operation, take a moment to familiarize yourself with the system while verifying that all components
are properly connected.
1. Verify that the hydraulic pressure (P), return (R), and drain (D) lines are connected.
2. Verify that the supply side HSM pressure (P), return (R), and drain (D) lines are connected.
3. Verify that the output side HSM pressure (P), return (R), and drain (D) lines are connected.
MTS TestLine Test System Operation | 55
Running the Example HCF Test