Rockwell Automation 1757-SWKIT400 Getting Started with ProcessLogix R400.0 Quick Start User Manual

Page 16

Advertising
background image

16 Getting Started with ProcessLogix R400.0

Publication 1757-QS040A-EN-P - October 2001

7. Locate the Labx I/O modules in the CEE0101 folder of the Project tab.

8. Load the IOMs by doing the following:

a. Select all of the IOMs in the I/O list area.

b. Click the green down arrow (load) in the toolbar.

The Load dialog box appears.

c. Verify that the I/O modules are all checked and click OK.

The assigned I/O modules appear under their CPM in the Monitor and
Project tabs.

TIP

To locate the IOMs, you may need to expand the CEE and I/O
branches of the tree in the Project tab.

ATTENTION

!

Load only the I/O modules that physically exist in the chassis.

TIP

In Monitoring tab:

blue indicates “inactive,”

green indicates “active and OK.”

red indicates “active and failed.”

Double-click the I/O module in the Monitoring tab to see
connection status on the Module Configuration tab.

Advertising