Required Steps

Installing the power structure(s) in an enclosure involves the following major
steps:

1. Select and prepare the enclosure(s)
2. Install the AC choke(s) - AC input drives only
3. Install and ground the power structure(s)
4. Connect the internal power cables
5. Install the control frame
6. Connect the control wiring
7. Install the du/dt filter(s) - frame 14 drives only (if ordered)
8. Install any options

Product Handling

Standard Components (see illustrations below)

Power Structure(s) - NFE converters and inverters (see

Table 1

and

Table 2

on

page 3

for the number of power structures provided with each frame

size)

AC choke(s) - AC input drives only
du/dt filter(s) - for frame 14 only (if ordered)
Control frame with HIM assembly
Control Cable Set - includes fiber optic cables and 24V connecting cable

(connects power structure and the control frame).
Standard length of 2.3 m (7.5 ft)

Frames 12 and 14 include a fiber optic cable set for internal control

connections between power structures

IMPORTANT

All power cables, busbars, enclosures, enclosure options and mounting
hardware are customer supplied.

AC Choke

Control Frame w/HIM Assembly

Control Cables

Power Structure

du/dt Filter