EVACUATING

Hexagonal wrench is required.

AIR PURGE

Evacuate the air in the connecting pipes and in the
indoor unit using vacuum pump.
Do not use the refrigerant in the outdoor unit.
For details, see the manual of vacuum pump.

Use a vacuum pump

Be sure to use a vacuum pump with counter-flow
prevention function so that inside oil of the pump does
not flow backward into pipes of the air conditioner
when the pump stops.

1. Connect the charge hose from the manifold valve

to the service port of the gas side packed valve.

2. Connect the charge hose to the port of vacuum

pump.

3. Open fully the low pressure side handle of the

gauge manifold valve.

4. Operate the vacuum pump to start evacuating.

Perform evacuating for about 35 minutes if the
piping length is 30 meters total for model SM560
and 50 meters for model SM800, SM1100, SM1400
(assuming a pump capacity of 27 liters per minute.)
Then confirm that the compound pressure gauge
reading is –101 kPa ( –76 cmHg).

5. Close the low pressure side valve handle of gauge

manifold.

6. Open fully the valve stem of the packed valves

(both sides of Gas and Liquid).

7. Remove the charging hose from the service port.

8. Securely tighten the caps on the packed valves.

Packed valve handling precautions

• Open the valve stem all the way out ; do not try to

open it beyond the stopper.

• Securely tighten the valve stem cap at the torque as

follows:

15.9 mm (diam.)

12.7 mm (diam.)

9.5 mm (diam.)

6.4 mm (diam.)

68 to 82 N•m (6.8 to 8.2 kgf•m)

50 to 62 N•m (5.0 to 6.2 kgf•m)

33 to 42 N•m (3.3 to 4.2 kgf•m)

14 to 18 N•m (1.4 to 1.8 kgf•m)

Open valve fully

Open valves of the corresponding outdoor units fully.

Gas leak check

Using a lead detector or soap water, check there is no
gas leak from pipe connecting portion or caps of the
valves.

REQUIREMENT

For a leak detector, use one manufactured
exclusively for HFC refrigerant (R410A, R134a, etc.)

Thermal-insulating process

Perform pipe thermal-insulating process for liquid and
gas sides separately.

• For thermal insulator to pipes at gas side, use one

with heat resisting temperature 120°C or higher.

• Using the attached thermal insulator, perform surely

thermal insulation without gap for pipe connecting
portion of the indoor unit.

REQUIREMENT

Perform surely thermal insulation process so that
the naked end of pipe connecting portion of the
indoor unit does not appear.
(Exposure of the pipe may cause water leak.)

Main unit

Union

Attached thermal insulator

Flare nut

Pipe thermal
insulator