06 connect work cable, Installation pak 200 – Tweco Pak 200 User Manual

Page 33

Advertising
background image

Manual 0-5057

3-7

INSTALLATION

INSTALLATION

PAK 200

3.06 Connect Work Cable

1. Pass the end of the work cable upward through the leads bracket at the bottom of the power supply rear panel,

then up through the opening in the connections cover support panel.

2. Refer to the illustration. Connect the lead as shown. Tighten securely. Do not overtighten.

WARNING

Ensure that lead attachment hardware is properly sized. Excess length may cause damage if hardware

contacts other parts of the system.

The clear connections cover must remain in place.

PILO

T

WORK

TORCH

Input power cable

Ground Terminal Block

Connections Cover
Support Panel

Art # A-08501

Connections Cover

Connection Panel

Leads Bracket

AC INPUT

Input power cable ground

L1 L2 L3

L1

L2

L3

Figure 3-7: Connect Work Cable