12 complete the installation, Pak 200 installation – Tweco Pak 200 User Manual
Page 42
INSTALLATION 3-16
Manual
0-5057
PAK 200
INSTALLATION
3.12 Complete the Installation
1. Fill the coolant tank to the level shown, with Thermal Dynamics coolant. The coolant level is visible through the
translucent coolant tank. The amount of coolant required varies with torch leads length.
2. Replace the cap on the tank.
Coolant Capabilities
Cat. Number and Mixture
Mixture
Protects To
7-3580 ‘Extra-CoolTM’
25 / 75
10° F / -12° C
7-3581 ‘Ultra-CoolTM’
50 / 50
27° F / -33° C
7-3582 ‘Extreme-CoolTM’
Concentrat*
-65° F / -51° C
*For mixing with D-1 CoolTM 7-3583
Table 3-17: Coolant Capabilities
RETURN
SUPPLY
RETURN
SUPPLY
Art # A-04803
COOLANT
Fill Range
Coolant Tank
Figure 3-18: Coolant Fill-to Illustration
3. After the complete system has been installed, check that the coolant has been pumped through the system as
follows (see NOTE):