1: Install junction box and low-voltage power.

2: Measure and mark installation length, allowing for 0.75"
extra space at junction box for power end cap and 1.0" inch
at the end of the installation for the take-up box. Cut
out marked areas using appropriate tools.

1

WALL

CEILING

JUNCTION
BOX

0.75"

1.0"

DESIRED LIT LENGTH

DESIRED LIT LENGTH

3: Insert the joiner bars halfway into the channel trap door
frame. Tighten the two #4-40 set screws on each joiner bar
with a 0.05" Allen wrench.

4: Slide the other section of channel onto the joining bars and
tighten the remaining #4-40 set screws with a 0.05" Allen
wrench.

5: Snap the lens into all channel sections BEFORE cutting to
length. This ensures a proper fit after installation.

4

CHANNEL

JOINER
BAR

TRAP DOOR
FRAME

TRAP DOOR
FRAME

LENS

6: Mark the desired lit length on the assembled channel and lens lengths.

45°

45°

7: Miter cut each section of assembled channel and lens to
match the corner angle. In a 90° inside corner installation
as shown, each channel section is cut at a 45° angle to
form a complete corner.

SIDE VIEW

Z5

7

7

ANGLE VIEW

Z2

Z3

2

3

5

6

MARK DESIRED LIT LENGTH

ASSEMBLED LENS AND CHANNEL w/TRAP DOOR FRAME

ADDITIONAL CHANNEL AND LENS SECTIONS AS REQUIRED

Z4

Advertising