12 frame install, Frame installation – Oldcastle BuildingEnvelope Reliance-TC User Manual

Page 12

Advertising
background image

R E L I A N C E - T C C U R T A I N W A L L I N S T A L L A T I O N M A N U A L

TM

FRAME INSTALLATION

3"

C Mullion

L

Front View at Sill

13
16

"

1

1

16

"

Side View at Sill

FIGURE 6

Type I Shear Block Orientation

and Single Span Perimeter Anchor

1
2

"

5

16

"

2

1
4

"

5

16

"

2.1.2 Install verticals plumb and level. Place shims under vertical mullion and anchor at sill to evenly

distribute deadload from wall. Install pipe sleeve anchor at head to allow for thermal movement of the vertical

mullions. SEE FIGURE 7, page 13 .

Anchor type and sizes vary per job requirements. Details shown in these instructions are to be used as a guide only.

Refer to approved shop drawings for actual conditions.

2.1 Vertical mullion installation:

SINGLE SPAN INSTALLATION:

2.1.1 Attach shear blocks to all vertical mullions. The integral perimeter anchors are designed for use with

standard shear blocks. Note; the WW-104-01 anchor may not be used with Type II head or sill horizontals having an
"AW" part number. SEE FIGURE 6 for proper orientation and installation on mullion.NOTE: Depending on the end

reactions, either the integral perimeter anchor or tee anchors can be used to anchor the wall. For end
reactions above 750 pounds, use "T" anchors.

See approved shop
drawings for anchor
sizing

FS-9 shear block
fastener

This shim must not interfere with
the mullion end cap.

WW-181-01 shear block

WW-104-01 perimeter anchor can

not be used with System 2 head and

sill assemblies

Shear Block Orientation
at Horizontal
(Head & Sill Similar)

WW-181-01
Shear Block

WW-104-01
perimeter
anchor

MAY 2013

12