4.2.1 Required Tools & Instrumentation

The following tools and instrumentation are necessary to perform combustion calibration of the
unit:

• Digital Combustion Analyzer: Oxygen accuracy to ± 0.4%; Carbon Monoxide (CO) and

Nitrogen Oxide (NOx) resolution to 1PPM.

• 16 inch W.C. manometer or equivalent gauge and plastic tubing.
• 1/4 inch NPT-to-barbed fittings for use with gas supply manometer or gauge.
• Small and large flat blade screwdrivers.
• Tube of silicone adhesive

4.2.2 Installing Gas Supply Manometer

The gas supply manometer (or gauge) is used to monitor the gas pressure on the downstream
side of the SSOV during the Combustion Calibration procedures described in section 4.4.

The gas supply manometer is installed at the downstream location shown in Figure 4-1.

Figure 4-1: 1/4 Inch Gas Plug Location for Combustion Calibration

DOWNSTREAM SSOV WITH
POC SWITCH

LOW GAS PRESSURE
SWITCH (8.5” W.C.)

TO AIR/FUEL

VALVE

GAS

INLET

LOW GAS

PRESSURE

SWITCH

(6.9” W.C.)

HIGH GAS

PRESSURE

SWITCH

(10.5” W.C.)

1/4" NPT PLUG
(Install Manometer here for Combustion Calibration)

MANUAL SHUT-OFF VALVE

LEAK

DETECTION

BALL VALVE