Benchmark 750/1000 Boiler

CHAPTER 10. BOILER SEQUENCING TECHNOLOGY

OMM-0082_0J

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

Page 131 of 192

GF-130

Ph.: 800-526-0288

05/21/2014

10.3.5 Option 5 - Remote Setpoint with DIRECT WIRED Header Sensor AND 4-
20ma Setpoint Drive


NOTE:
Both Header Sensor AND 4-20ma Direct Drive must be wired. See the C-More
Controller User Manual, OMM-0032, GF-112 and ProtoNode User Manual, OMM-0080, GF-129
for more information.

Step 1: Direct Wired Header Sensor Wiring

1. On the MASTER Unit, Connect the Header Temperature Sensor (AERCO PN 61040) to the

Feed Forward (FFWD) terminals on the P-1 Harness Via the terminal block labeled “Header
Temp sensor” in the I/O Box.


NOTES:

• The header sensor must be installed between 2 and 10 feet downstream of the LAST boiler

in the plant’s supply water header.

• Shielded pair 18 - 22 AWG cable is recommended for header sensor wiring.

• There is no polarity to be observed.

• The ground for the shield is at the “SHLD” terminal in the I/O the Box.

• The sensor end of the shield must be left free and ungrounded.

Step 2: Direct Wired 0-20ma or 4-20ma Wiring

1. Connect the 4-20ma or 0-20ma terminals from the Direct Drive source to the Ain+ and Ain-

terminals on the Master Unit’s I/O Box.


NOTE:

• Shielded pair 18 - 22 AWG cable is recommended for this connection. Polarity must be

observed.

• The ground for the shield is at the driver signal source.

Temp Sensor PN 61040

Header Temp Sensor

I/O Box

I/O Box

Advertising