10.3.8 Option 8 - Remote Setpoint with MODBUS Header Sensor AND MODBUS
Setpoint Drive


NOTE! Both Header Sensor AND ProtoNode SSD Device must be wired. See the C-More
Controller User Manual, OMM-0032, GF-112 and ProtoNode User Manual, OMM-0080, GF-129
for more information.

Step 1: MODbus Header Sensor

1. Using Shielded pair 18 - 22 AWG cable, Connect the Temperature Transmitter (AERCO P/N

65169) terminal Pin B to the RS485+ terminal on the I/O Box of any of the Boiler units, and
Pin A of the Temperature Transmitter to the RS485- terminal on the I/O Box of any of the
Boiler units.

2. Using Shielded pair 18 - 22 AWG cable, connect the Modbus Header Temperature Sensor

(AERCO PN 24410) to pins 2 and 3 of the Temperature Transmitter.

3. Install a jumper wire between pins 1 and 2 of the Temperature Transmitter.


NOTES:

• Polarity must be observed for the RS485 connections. The ground for the shield is at the

“SHLD” terminal in the I/O the Box.

• The header sensor must be installed between 2 and 10 feet downstream of the LAST boiler

in the plant’s supply water header.

• There is no polarity to be observed. The ground for the shield is at the power supply

ground. The sensor end of the shield must be left free and ungrounded.


Step 2: Remote Setpoint with Network

1. Configure and Connect the SSD Device (ProtoNode) per the AERCO Manual (GF129).

Temp Sensor PN 24410

Modbus Transmitter